Rajiv Gandhi Grameen Vidyuthikaran Yojana (RGGVY)

I. Ongoing Scheme (XIth Plan)

REC has sanctioned the revised DPR submitted by KSEB for implementation of RGGVY in Kasargod, Kannur, Kozhikode, Wayanad, Palakkad and Malappuram districts, on 10.03.2010 for total outlay of Rs. 114.57 crore.

Financial details are as shown below:

Scheme

Sanctioned Amount

Amount received from REC

 

 

Grant

Loan

Total

Kasargod

1460.71

686.8110

77.0915

763.9025

Kannur

1971.40

859.6040

96.4656

956.0695

Kozhikode

1692.93

750.3249

85.5839

835.9089

Wayanad

1433.44

585.2222

66.0307

651.2529

Palakkad

1635.40

672.8242

75.4930

748.3172

Malappuram (VEI+REDB)

3263.46

1503.9291

168.5703

1672.4994

Total

11457.34

5058.7154

569.23497

5627.9504

As per the condition of sanction, turnkey tenders were invited and the work was awarded to the following contractors.

Sl. No

Name of District

Amount of Contract in Rs. Lakh

Name of Contractor

Work awarded date

Target date of completion as per REC

1

Kasargod

1246.124

M/s Bentec Electrical& Electronics, Kolkatta

31.08.10

31.08.12

2

Kannur

1561.760

M/s Bentec Electrical& Electronics, Kolkatta

08.09.10

08.09.12

3

Kozhikode

1223.592

M/s Bentec Electrical& Electronics, Kolkatta

27.11.10

27.11.12

4

Wayanad

1027.234

M/s Aravali Infra Power Limited (AIPL), New Delhi.

16.11.10

16.11.12

5

Palakkad

1223.632

M/s Aravali Infra Power Limited (AIPL), New Delhi.

29.01.11

29.01.13

6

Malappuram (VEI)

1926.170

M/s East Coast Constructions & Industries Ltd, Chennai.

29.03.11

29.03.13

REDB

826.663

M/s Aster Pvt Ltd, Hyderabad

23.08.11

29.03.13

 

M/s CPRI has been entrusted as Third Party Inspection Agency for Three Tier Quality Inspection Mechanism.

Revised cost estimate submitted for sanction for the 6 northern districts  

(Kasargod, Kannur, Kozhikode, Wayanad, Palakkad and Malappuram).

       Due to the difficult terrain conditions the quantum of materials increased especially in the case of stay sets. The cost estimate were revised and submitted to REC for getting sanction for the revised cost estimate during July 2012 and are furnished below

Scheme

Sanctioned Amount

Revised Amount

Kasargod

1460.71

1609.60

Kannur

1971.40

2959.95

Kozhikode

1692.93

1973.01

Wayanad

1433.44

1894.77

Palakkad

1635.40

1987.93

Malappuram (VEI+REDB)

3263.46

3770.95

Total

11457.34

14196.21

The progress of the work:

 

  1. KASARGOD DISTRICT:

          Physical progress:

          Work in 299 kara completed (Total Kara as per revised DPR – 1209)  

          Work in 26 Villages completed. (Total Villages as per revised DPR – 103)        

 

          No. of BPL Service connections effected: 73 Nos

          No. of BPL service connections effected from existing infrastructure: 2491 Nos

 

  1. KANNUR DISTRICT:

          Physical progress:

          Work in 175 Kara completed (Total Kara as per revised DPR – 834)

          Work in 5 Villages completed. (Total village as per revised DPR – 124)

 

          No. of BPL service connections effected: 476 Nos

          No. of BPL service connections effected from existing infrastructure: 4645 Nos

 

     3. KOZHIKODE DISTRICT:

         Physical progress:

         Work in 332 kara completed. (Total Kara as per revised DPR – 1600)

         No. of BPL service connections effected from existing infrastructure: 5116 Nos

 

  1. WAYANAD DISTRICT:

          Physical progress:

          VEI work:

          Work in 58 kara completed (Total Kara as per revised DPR – 275)

          Work in 7 Villages completed. (Total Villages as per revised DPR – 48)

 

          No. of BPL service connections effected: 149 Nos

          No. of BPL service connections effected from existing infrastructure: 5160 Nos

 

          REDB work: GTP yet to be submitted by the Contractor

 

  1. PALAKKAD DISTRICT:

          Physical progress:

          VEI work:

          Work completed in 2 kara

          Work in progress in 31 kara. (Total Kara as per revised DPR – 878)

 

          No. of BPL service connections effected: 36

          No. of BPL service connections effected from existing infrastructure: 9228 Nos

 

          REDB work: GTP yet to be submitted by the Contractor

 

  1. MALAPPURAM DISTRICT:

          Physical progress:

          VEI work: Work in progress in 17 Karas (Total Kara as per revised DPR – 615)

 

          No. of BPL service connections effected: 187

          No. of BPL service connections effected from existing infrastructure: 5488 Nos

 

        REDB work: Survey completed. Approved the Single Line Diagram submitted by the

        Contractor. Land development work in progress.

 

   Physical Details is attached as Annexure.

 

II. Schemes for remaining 7 districts:

Sanction has been issued by REC on 19.12.2011 for implementation of RGGVY in Alappuzha, Kollam, Pathanamthitta, Kottayam and Thrissur districts for an amount of Rs. 4329.72 lakhs and on 14.02.2012 for implementation of the scheme in Ernakulam and Thiruvananthapuram districts for an amount of Rs 4653.37 Lakhs. The letter for accepting all the terms and conditions of sanction is submitted to REC from Govt. of Kerala for these 7 districts.

Sl. No

District

Sanctioned Cost

in Rs. Lakh

1

Thiruvananthapuram

2182.13

2

Kollam

328.05

3

Pathanamthitta

575.65

4

Alappuzha

1366.81

5

Kottayam

796.51

6

Ernakulam

2471.24

7

Thrissur

1262.70

 

Total

8983.09

     As decided in the meeting held on 04.03.2012 at Kannur, chaired by the Hon’ble Minister of State for Power, Govt. of India, Board has accorded sanction to execute the work under the scheme directly by procuring material and engaging the labours departmentally. In principle approval has been received from REC.

 

Idukki II phase scheme:

    RGGVY scheme was implemented in Idukki district. 17238 BPL households were electrified under this scheme. Closure proposal is submitted to REC. DPR for Idukki II phase scheme for an amount of Rs. 1924.20042 Lakhs to REC for getting approval to execute the work departmentally during January 2012.
RGGVY - Physical Status - as on 16.08.2012

Sl. No.

Particulars

Kasargod

Kannur

Kozhikode

 

Sanctioned Qty.

Revised Qty

Progress

% against revised Qty

Sanctioned Qty.

Revised Qty

Progress

% against revised Qty

Sanctioned Qty.

Revised Qty

Progress

% against revised Qty

 

1

Villages

113

103

26

 

78

124

5

 

87

127

 

 

 

2

Kara

382

1209

299

 

576

834

175

 

897

1600

332

 

 

3

LT SP Line(Km)

366.088

298.0669

133.890

44.92

239.29

482.178

181.95

37.74

251.67

340.500

53.999

15.86

 

4

LT 3P line(Km)

47.473

36.5200

13.900

38.06

99.25

125.987

62.470

49.58

65.29

40.220

7.391

18.38

 

5

11 KV Line (Km)

60.73

88.4400

46.210

52.25

139.46

212.970

110.210

51.75

105.41

137.035

49.703

36.27

 

6

Transformers (25 KVA) (Nos)

113

98

43

43.88

283

255

92

36.08

163

129

32

24.81

 

7

11 KV XLPE 3x300 UG Cable (Km)

 

1.75

 

 

 

 

 

 

 

 

 

 

 

8

3 Phase 3.5 core 240 sq.mm UG Cable (Km)

 

2.05

 

 

 

 

 

 

 

 

 

 

 

9

S Phase 2 core 240 sq.mm UG Cable (Km)

 

1.6

 

 

 

 

 

 

 

 

 

 

 

10

BPL service Connections (Nos)(New)

4194

6221

73

 

5136

8670

476

 

11920

9350

0

 

549 

11

BPL S/c from existing infrastructure

 

 

2491

 

 

 

4645

 

 

 

5116

 

 

12

Total S/c effected

 

 

2564

 

 

 

5121

 

 

 

5116

 

12801 

13

REDB work

 

 

 

179.11

 

 

 

175.15

 

 

 

95.31

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

44.78

 

 

 

43.79

 

 

 

23.8

 

RGGVY - Physical Status - as on 16.08.2012

Sl. No.

Particulars

Kozhikode

Wayanad

Palakkad

 

Sanctioned Qty.

Revised Qty

Progress

% against revised Qty

Sanctioned Qty.

Revised Qty

Progress

% against revised Qty

Sanctioned Qty.

Revised Qty

Progress

% against revised Qty

 

1

Villages

48

48

7

 

144

140

 

 

122

139

 

 

 

2

Kara

316

275

58

 

788

878

2

 

589

615

 

 

 

3

LT SP Line(Km)

160.800

249.500

54.804

21.97

107.855

247.724

12.17

4.91

329.066

495.420

10.840

2.188

 

4

LT 3P line(Km)

33.930

50.400

14.36

28.49

57.230

40.434

4.88

12.07

108.550

65.010

2.499

3.844

 

5

11 KV Line (Km)

136.950

165.300

46.00

27.83

190.310

155.389

35.04

22.55

182.710

236.020

4.81

2.039

 

6

Transformers (25 KVA) (Nos)

216

155

27

17.42

137

165

16

9.70

330

248

0

0.00

 

7

11 KV XLPE 3x300 UG Cable (Km)

 

 

 

 

 

 

 

 

 

 

 

 

 

8

3 Phase 3.5 core 240 sq.mm UG Cable (Km)

 

 

 

 

 

 

 

 

 

 

 

 

 

9

S Phase 2 core 240 sq.mm UG Cable (Km)

 

 

 

 

 

 

 

 

 

 

 

 

 

10

BPL service Connections (Nos)(New)

7278

9897

149

 

4970

11009

36

 

7897

10818

187

 

372

11

BPL S/c from existing infrastructure

 

 

5160

 

 

 

9228

 

 

 

5488

 

 

12

Total S/c effected

 

 

5309

 

 

 

9264

 

 

 

5675

 

20248

13

REDB work

Enhancement of 33/11 KV s/s by adding one 5 MVA TFR

 

 

95.70

Enhancement of 33/11 KV s/s by adding one 5 MVA TFR

 

 

49.23

66/11 KV S/s, 2.5 KM 66 KV DC line with 110 KV parameter, 4 KM 11 KV line.

 

Land development in progress.

8.071

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

23.92

 

 

 

12.31

 

 

 

2.02

 


 

mod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_counter
mod_vvisit_counterToday15124
mod_vvisit_counterThis month354909
Licensed Under CC BY-SA 2.5 IN. Designed and maintained by KSEB IT Regional Unit,Kozhikode